New York Construction
Strong Foundation Supports Eighth Avenue Tower
- Tom Stabile
January 01, /2004
Marc rises 432ft into the city skyline, with a soaring
crown accented by a flying column design.
But some of the most impressive work in the 435,000ft
structure at 900 Eighth Ave. took place out of sight
and in the structural underbelly of a classically compact
Manhattan property.
Beneath this 45 - story giant is a muscle grid of cassion
support, concrete walls and clusters of steel bars that
help the structure straddle two subway tunnels that
cross through the site.
The project schedule was tight. Excavation started
in October 2002, the reinforced concrete superstructure
was topped out in September and the building is slated
for full occupancy this summer.
The project takes advantage of the promise in the Eight
Avenue corridor, said Joseph Moinian, Chairman of the
Moinian Group, the New York, N.Y. - based developer.
"When the site became available in 1999 we took
the opportunity," he added. "In addition,
full - block sites are very rare in New York City, especially
an income producing site."
The $ 76 million building, designed by Frank Williams
and Associates of New York, N.Y., will have 393 apartments
on 37 floors; ground - floor retail; a four - storey,
550 - car garage; and a common floor with a health club,
laundry room, child care center and other amenities.
Jack Kestenbaum, project manager for HRH constructions
of New York, N.Y., said it took value engineering and
scheduling to keep MARC on track.
"We came up with alternatives to make sure we
could get to each stage on schedule," he added.
First came careful focus on the foundation and using
solutions designed by structural engineer Rosenwasser
Grossman Consulting and executed by foundation contractor
Civetta Cousins Joint Venture and concrete contractor
Century-Maxim Construction Corp.
Demolition of an existing municipal parking garage
took place before HRH arrived on the job. When HRH took
over, work to support the future building's load began
with a caisson design.
The Civetta Cousins team began by driving thick structural
steel tubes into the bedrock on either side of the tunnels
for the B and D lines of the NYC Transit Authority,
which turn under the site. Next, workers excavated around
the piles and anchored clusters of reinforced steel
bars to the rock throughout that area. Then the entire
complex was encased in concrete.
Once Civetta Cousins completed that phase, Century
-Maxim erected giant concrete walls to support the foundation.
"The way the engineer designed it to accommodate
that was to create large structural beams, but they
were huge supporting walls that were 20 ft or more high,"
said Tom Cardullo of Century Maxim. "They allow
the foundation floor to bridge over the subway without
putting any load on the tunnel."
|